Construction Update | June 12, 2013

Transportation & Emerging Technologies Renovation Project

Phase I Construction Update
June 12, 2013

A new electrical substation was installed Monday, June 10, replacing two old substations. Over the next seven weeks, workers will switch electrical loads to the new substation, including all outlets and switches for the entire 118,000-square-foot space undergoing renovation.

Workers will install a new air handler in Pod #16 Thursday, June 13. Air handlers will be installed in Pods #14 and #15 by the end of the week of June 17.

A steel second deck has been added to the new Welding Technology program area. The deck will house air handling, dust collection and load center equipment for the welding shop. Work on the roof will be complete by Friday, June 14. New tar was applied to repair roof areas affected by duct and ventilation work.

New walls are going up for the new, multiuse classrooms that will be due north and adjacent to the GM ASEP and Automotive Technician program areas (Shops #5 and #6). All new flammable tanks have been installed in the Transportation area shops. Assorted demolition, plumbing and HVAC work continues.    

Phase I Photo Gallery

120

Photo 120

119

Photo 119

118

Photo 118

117

Photo 117

116

Photo 116

115

Photo 115

114

Photo 114

113

Photo 113

112

Photo 112

111

Photo 111

110

Photo 110

109

Photo 109

108

Photo 108

107

Photo 107

106

Photo 106

105

Photo 105

104

Photo 104

103

Photo 103

102

Photo 102

101

Photo 101

100

Photo 100

99

Photo 99

98

Photo 98

97

Photo 97

96

Photo 96

95

Photo 95

94

Photo 94

93

Photo 93

92

Photo 92

91

Photo 91

90

Photo 90

89

Photo 89

88

Photo 88

87

Photo 87

86

Photo 86

85

Photo 85

84

Photo 84

83

Photo 83

82

Photo 82

81

Photo 81

80

Photo 80

79

Photo 79

78

Photo 78

77

Photo 77

76

Photo 76

75

Photo 75

74

Photo 74

73

Photo 73

72

Photo 72

71

Photo 71

70

Photo 70

69

Photo 69

68

Photo 68

67

Photo 67

66

Photo 66

65

Photo 65

64

Photo 64

63

Photo 63

62

Photo 62

61

Photo 61

60

Photo 60

59

Photo 59

58

Photo 58

57

Photo 57

56

Photo 56

55

Photo 55

54

Photo 54

53

Photo 53

52

Photo 52

51

Photo 51

50

Photo 50

49

Photo 49

48

Photo 48

47

Photo 47

46

Photo 46

45

Photo 45

44

Photo 44

43

Photo 43

42

Photo 42

41

Photo 41

40

Photo 40

39

Photo 39

38

Photo 38

37

Photo 37

36

Photo 36

35

Photo 35

34

Photo 34

33

Photo 33

32

Photo 32

31

Photo 31

30

Photo 30

29

Photo 29

28

Photo 28

27

Photo 27

26

Photo 26

25

Photo 25

24

Photo 24

23

Photo 23

22

Photo 22

21

Photo 21

20

Photo 20

19

Photo 19

18

Photo 18

17

Photo 17

16

Photo 16

15

Photo 15

14

Photo 14

13

Photo 13

12

Photo 12

11

Photo 11

10

Photo 10

9

Photo 9

8

Photo 8

7

Photo 7

6

Photo 6

5

Photo 5

4

Photo 4

3

Photo 3

2

Photo 2

1

Photo 1

 
For more information about Phase I of the Transportation & Emerging Technologies Renovation Project, contact:

Previous Construction Updates